Navigating contract negotiations is a critical phase in the tendering process, particularly for local governments seeking to finalise agreements with their preferred tenderer. In the fifth and final instalment of our Probity, Procurement and Tendering Series, this article explores the key elements of effective negotiations and provides practical insights into developing a negotiation strategy, maintaining competitive tension and ensuring that the negotiation process is transparent, fair, and legally compliant.
The objectives of a local government procurement policy are generally to advance the local government’s priorities, achieve value for money, and ensure probity and accountability for outcomes.
Probity requires the purchase to be conducted ethically, honestly, and with fairness to all participants. Accountability for outcomes is about being able to explain or account for how the purchase has achieved its anticipated outcomes. Best practice in government procurement would see the development of a suitable probity plan, and for high value or complex procurement activities, the development of the plan well before the commencement of the procurement process, as well as the engagement of an external probity adviser.
This article serves as a checklist of tasks in chronological order which can form the basis for a probity plan.
The below article on Tender Process Risks and Strategies to Mitigate is the third article in our five-part Probity, Procurement and Tendering Article Series. This article will be followed by articles on Probity Plans, and lastly Contract Negotiations. This article explores strategies for minimising risks in the tender process, for both procurers and tenderers.
For procurers, we discuss key strategies for risks associated with:
For tenderers, we discuss key strategies for risks associated with:
We also discuss “Closing the deal” and the risks associated with:
This article on tendering and process contracts is the second article in our five-part Probity, Procurement and Tendering Article Series.
Requests for Tender (RTFs) have traditionally been viewed as invitations to treat, that do not create a legal or contractual obligation until a tender is accepted by the party inviting the tenders. However, a process contract can arise as are sult of a term within an RTF that constitutes an offer, which when accepted or complied with (generally by the tenderer submitting its tender) brings about a separate binding contract, or “process contract”. The implications of a process contract can be far reaching, due to the legal obligations that arise. As a result, the party inviting tenders must pay close attention to the tender process and draft the RFT to reduce the risk.
Managing process contract risk requires the procurer to:
In Queensland a Payment Claim must:
In the recent case of MWB v Devcon , the Contractor (Devcon) was engaged to construct 56 townhouses. They sent what they said was a payment claim to the Principal which purportedly claimed payment of $149,485.60 by reference to a table listing 42 trades and showing a ‘contract value’, ‘amount previously claimed’, % complete’, and ‘remaining balance’ for each trade.
The Court of Appeal found that the purported payment claim was not a payment claim under s68 of the Building Industry Fairness (Security of Payment) Act 2017 (Qld) (BIF Act) because it failed to comply with s68(1)(a), (b) or (c).
IOdeally, parties to a contract would always fulfil all their obligations. Unfortunately, for often entirely
innocent reasons, that is not always the case. Contract breaches remain a common challenge, with potential legal, financial and reputational consequences depending on their severity. This article explores the implications of contract breaches and strategies to address and mitigate
any resulting issues effectively.
This is article two in our 6-part series on contract law and administration. We started the series with a contract law refresher, with articles on time, payment and security of payment, legal implications of contract breaches and post contract award contract management to follow over the course of the next four weeks.
Contractual variations can assist parties to swiftly navigate unforeseen changes to a contract throughout the life of the project but can also cause major problems if not negotiated and implemented appropriately.
This is article three in our 6-part series on contract law and administration. We commenced our series with a contract law refresher followed by a high- level summary of contractual variations, with articles on payment and security of payment, legal implications of contract breaches and post contract award contract management still to come.
In Part 1 of this article series, we looked at strategies for adequately planning a procurement process, process contracts and managing risk in the planning stage. In part 2 of this article series, we consider the legal and probity implications for procurers and tenderers after the release of tender documents, strategies for procurers and tenderers, how to deal with conforming and non-conforming bids and closing the deal.
The dictionary definition of “probity” refers to honesty, proper and ethical conduct, uprightness and propriety in dealings with others. Good probity practices means ensuring that tenderers will be treated fairly, impartially and equitably, adopting and applying a consistent methodology in the assessment of tenders and ensuring a consistently applied and transparent process.
Tendering for contracts, whether as procurer or supplier, is difficult and requires each party to consider a number of different factors. In this article, we discuss the key considerations that procurers and suppliers must have prior to the release of a tender.
Procurement planning is an essential first step in the tender process and will assist in achieving desired procurement outcomes and in mitigating negative legal implications. When approaching the market for the delivery of a service, product or works, there a multitude of questions that a procurer should seek to answer. These questions will depend on the specific circumstances of the project and the market, but the broad questions that procurers should (at minimum) be asking themselves are as follows